Submitted by Town Engineer Adrienne St. John
If the weather cooperates, School Way Project contractor ET&L will
- Pour concrete sidewalks on School Way and Maple Street on Monday (10/27)
- Hydro seed loamed areas on Tuesday (10/28)
- Add the top course of pavement on School Way, Maple Street and Elm Street on Friday (10/31)
- Pave the asphalt driveways on School Way, Maple Street, and Elm Street on Monday (11/3) & Tuesday (11/4)
Editor’s Note: Residents should expect delays and road closures during road paving