Submitted by Public Works Engineer Adrienne St. John
The Bedford Selectmen recently awarded a contract to Sunshine Paving to refurbish the stone dust path along the Narrow Gauge Rail Trail between Great Road and the Billerica town line.
Click Narrow Gauge Map to see the full, scalable map.
The work includes removal of the existing material to reestablish a 10 foot wide compacted stone dust path. The two parking areas will also be reworked to provide a uniform grade and resurfaced with new stone dust.
The project is expected to begin on December 1st and be completed in approximately two weeks, weather dependent.
The Town will have a uniformed police detail at the work site to assist users to cross the construction area, but please use caution along the path.
For additional information, please contact the Department of Public Works at (781) 275-7605.