August 15 & 16 ~ Wednesday & Thursday
Crews will be removing manhole and catch basin covers.
August 17 & 20 ~ Friday and Monday
Sealcoating, Inc. equipment pulverizes and repaves initial course of asphalt
August 21 – 24 ~ Tuesday through Friday
Crews will raise manhole and catch basin covers; use caution when traveling around raised structures.
August 25 ~ Saturday
PJ Keating Co. paves finish course of asphalt, starting at 6 AM on Brooksbie Road and traveling east towards Burlington Road. Roads will be closed and detoured by section; please follow detour signs around the work zone.