Compiled by The Bedford Citizen
The Bedford Department of Public Works has scheduled milling and repaving of Davis Road and Great Road according to the following schedule:
The Great Road from Loomis Street to South Road ~ expect detours
- July 28 ~ Milling, from 8 pm to 6 am
- August 4 ~ Paving, from 8 pm to 6 am
Davis Road
- July 30 and 31 ~ Milling, from 7 am to 4 pm
- August 6 and 7 ~ Paving, from 7 am to 4 pm
In the event of rain, the work will be moved to the next available day.
Please contact the Department of Public Works at (781) 275-7605 if you have any questions or need additional information. Thank you for your patience.